Installation of curing oven (polymerisation chamber) line for building materials sector

Published: 4 March 2021

To install curing oven line including dust cleaning system and exhaust filters

  • Full mechanical and electrical scope of installation
  • Prefabrication and installation of steelwork platforms and walkways
  • Installation of exhaust and ventilation systems
  • Utilities connections
  • Over 40 truckload of deliveries
  • Over 13000 manhours worked
  • 6 months duration (October 2020 – March 2021)
  • Cooperation with OEMs
  • Contented customer