Published: 5 April 2022
- realisation in two stages:
- unloading, internal transport and positioning of line elements
- installation of equipment, connections and commissioning
- assembly using specialist equipment - hydraulic gantry 160t
- the project was executed from December 2021 to January 2022
- the task was completed quicker than the agreed deadline
- 2 000 manhours worked in single-shift system
- difficult conditions - height of the production hall, construction of transport road and fundaments - required precise planning from unloading to positioning of the machinery