Published: 26 November 2021
Installation and refurbishment works during a shutdown of a car tyre factory.
- Replacement of rolls on calender
- Replacement of screws on Triplex extruder
- Replacement of gearbox on Quadroplex extruder
- Full mechanical and electrical scope of works
- Project carried out during two-week summer shutdown (July 2021)
- Work in two-shift work system
- Over 2,500 man-hours
- Task completed under time pressure, in difficult conditions