Replacement of combustion chamber for polymerisation furnace

Published: 5 April 2022
  • unloading, internal transport of the new chamber
  • disconnection, isolation and dismantling of the old chamber
  • installation of a new chamber and insulation
  • assembly of equipment, connections and commissioning
  • the task was completed quicker than the agreed deadline, this enabled the furnace  and production to be started up earlier
  • work in two-shift system 24 hours a day
  • difficult conditions - height of the production hall, existing installations and limited access for lifting equipment