Revamping project carried out in car tyres factory

Published: 26 November 2021

Installation and refurbishment works during a shutdown of a car tyre factory.

  • Replacement of rolls on calender
  • Replacement of screws on Triplex extruder
  • Replacement of gearbox on Quadroplex extruder
  • Full mechanical and electrical scope of works
  • Project carried out during two-week summer shutdown (July 2021)
  • Work in two-shift work system
  • Over 2,500 man-hours
  • Task completed under time pressure, in difficult conditions