Published: 5 April 2022
- unloading, internal transport of the new chamber
- disconnection, isolation and dismantling of the old chamber
- installation of a new chamber and insulation
- assembly of equipment, connections and commissioning
- the task was completed quicker than the agreed deadline, this enabled the furnace and production to be started up earlier
- work in two-shift system 24 hours a day
- difficult conditions - height of the production hall, existing installations and limited access for lifting equipment